AFS Featured Projects
Whole Tire Feed System – Flip and Slide
Whole Tire Feed System - Flip and Slide Romcim Cement, Medgidia, Romania (2025-2026) - This system was engineered to adapt an existing tire-feeding line to a new precalciner combustion burner ...
Tire Feed System – Phase Two – Sephaku Cement, South Africa
Tire Feed System – Phase Two – Sephaku Cement, South Africa Sephaku Cement, South Africa (November 2024) - This was phase 2 of a whole tire fuel feeding system for ...
Whole Tire Feed System – Midlothian, Texas
Whole Tire Feed System - Midlothian, Texas Midlothian, Texas (2022) - This project involved designing and building a system to feed whole car tires and truck tires to an existing ...
Tire Feed System – Phase One – Sephaku Cement, South Africa
Tire Feed System - Phase One - Sephaku Cement, South Africa Sephaku Cement - Lichtenburg, South Africa (2022) - In June 2022, Phase 1 of a whole tire fuel feed ...
Whole Tire Feed System – Alpena
Whole Tire Feed System - Alpena Alpena Plant (Holcim) – Alpena, Michigan, USA (2022–2023) – AFS Technology delivered a turnkey, fully automated mid-kiln tire fuel feed system for the Holcim ...
Whole Tire Fuel Feed System – Nova Scotia
Nova Scotia, Canada (2018) - AFS Technology is providing a fully automated mid-kiln tire fuel feed system for the Lafarge Canada cement plant in Brookfield, Nova Scotia. The system will ...
Whole Tire Fuel Feed System – Argentina
LafargeHolcim Cement Plant - Puesto Viejo, Argentina (2017) - The system was designed to feed whole tires and bagged waste to a Double Gate Airlock Valve with Maintenance Gate mount to ...
Tire Feed System – Oklahoma
Bristow, Oklahoma (2016) - The tire feed system was designed to feed approximately 10 tons per hour of whole tires to the existing manual loading belt conveyor at the plant ...
Skewer Suspension Burner – Texas
Midlothian, Texas (2012) — Turnkey dual-fuel alternative-fuel feeding system for Kiln 5 at the TXI cement plant in Midlothian, Texas. This fully automated system fed whole tires from an existing ...
Tire Fuel System – South Africa
Simuma, South Africa (2010) – This whole tire feeding system was designed to automatically feed whole tires to the feed shelf of the 4-stage preheater kiln using a Double Gate ...
Tire Feed System – Romania
Medgidia, Romania (2008) - Whole Tire Fuel Feed System designed to accept tires manually loaded on a conveyor at ground level and automatically feed them to the feed shelves of ...
Tire Feed System – Romania
Hoghiz, Romania (2011) - Automatic tire fuel system with hook elevator and airlock valve. System designed to automatically feed whole tires to the feed shelf of a through an airlock ...
Tire Derived Fuel System – Florida
Newberry, Florida (2005) - Tire Derived Fuel System (TDF) designed to feed to precalciner kiln and includes trailer tipper, live bottom hopper, tire separator, separation refinement, inspection/rejection, modification of existing elevator, ...
Whole & Chipped Tire System – Puerto Rico
Ponce, Puerto Rico (2010) - System design and equipment for feeding , which includes two trailer tippers, two-stage live bottom hopper 80′ long, sealed live bottom hopper 40′ long, tire ...
Tire Feed System – Texas
Midlothian, Texas (2005) - A complete turnkey whole tire fuel handling system to feed existing long dry kiln. The equipment includes a trailer tipper, live bottom hopper, tire separator, separation ...
Tire Feed System – Alabama
Demopolis, Alabama (2008) - Whole tire feed system consulting work, in conjunction with Dover Conveyor, provided system design and equipment for feeding whole tires to one 4-stage preheater kiln, which included ...
Mid-Kiln Tire Feed System – Illinois
Lafarge Cement – Joppa, Illinois (2003)
Turnkey mid-kiln whole tire fuel handling system feeding two long dry kilns. The system included a trailer tipper, live bottom hopper, tire separator, accumulator, tire ...
Turnkey mid-kiln whole tire fuel handling system feeding two long dry kilns. The system included a trailer tipper, live bottom hopper, tire separator, accumulator, tire ...
Suspension Burning System – Chile
La Calera Plant — Chile - Completed: 2006 AFS provided the plant’s second rack suspension burner, expanding its ability to use whole tires as fuel in the kiln precalciner. The system ...
Tire Feed System – Texas
New Braunfels, Texas (2002) - AFS provided a turnkey, fully-automated whole tire feeding system for a 4-stage preheater kiln. This system included a trailer tipper, live bottom hopper, tire separator, tire ...
Mid-Kiln Tire Feed System – Oklahoma
Blue Circle Cement – Tulsa, Oklahoma (2002)
Turnkey mid-kiln whole tire fuel handling system feeding two long dry kilns. The system included a trailer tipper, live bottom hopper, tire separator, accumulator, ...
Turnkey mid-kiln whole tire fuel handling system feeding two long dry kilns. The system included a trailer tipper, live bottom hopper, tire separator, accumulator, ...
This Google powered map displays location and information about some of our featured projects around the globe. Check back frequently for new projects added.
For a complete list of AFS projects – click here to contact us